Richmond Valley Station

Owner
MTA New York City Transit
Contract #: A-36622F

Description
Station Finishes And State Of Good Repair Work At Richmond Valley Station (Sir) In The Borough Of Staten Island

Scope of Work
The Scope of this work included the rehabilitation of Platform and Canopy, Renovation of stairs, Extensive removal of lead-based paint and painting of Canopies and Stairs, Concrete repairs, Steel repair, Restauration of concrete beams below the platforms.

Dates
Award Letter was issued on March 15, 2018
Construction end Date March 14, 2019. This project was completed two months ahead of time on January 14th, 2019.
  • 22
  • 23
  • IMG_0981
  • IMG_1149
  • IMG_1175
  • IMG_1240
  • IMG_1288
  • IMG_1294
  • IMG_1391
  • IMG_1436
  • IMG_1492
  • IMG_2123
  • IMG_2124
  • IMG_2130