Roof and Enclosure at Gates Ave

Owner
MTA New York City Transit
Contract #: C-36694

Description
Rehabilitation of Roof and Enclosure at Gates Ave Ridgewood Substation in the Borough of Brooklyn

Scope of Work
This project involved the roofing system’s removal and replacement, including roof railing; surface cleaning, painting, concrete coping removal and replacement, cornice removal and replacement, brick removal & replacement, repointing; roof slab; steel repair, the removal and replacement of exhaust fans, dampers and associated control systems; roof drain removal and replacement; and electrical, power work at the Gates Ave / Ridgewood Substation.

Dates
Award letter was issued on April 6th, 2018
Construction end Date May 30th, 2019.